From your Chairperson
The 4th of July event was a success due to the efforts of Team 2, along with much appreciated help from Teams 1 & 3. We had a tri-tip dinner on Saturday and a pork roast dinner on Sunday, as usual the sides and desserts were outstanding as well as plentiful. If memory serves me correctly we had seventeen boats cruise in.
I believe next year we will have to have another realignment of Team members in an effort to get more of the active members spread evenly amongst the teams.
We had a failure of one piling at the tip of the Southernmost finger, due to the efforts of Frank and his merry band of helpers this repair was completed promptly so as not to interfere with the 4th of July event.
We are continuing to experience failure of the decking on the docks as well as the walkways and Sunset Deck. We had one member go through the dock at the foot of the north ramp and had a failure on the Sunset Deck in the last 30 days. Frank Louthan our Island Maintenance Manager has proposed that we spend the money to repair the docks in such a way as to extend the usability for 4-5 years before replacement. I believe this can be done for around $3500. or less. I am in favor of doing this and am currently awaiting response from the |
|
In This Issue
July 4th Pictures Page 02 Labor Day Flyer Page 12 Labor Day Sign-up Page 13
|
|
DI Doings |
|
July 2011 |
|
other Board Members before moving ahead with the project which would be started immediately and completed on non-cruise weeks. This project would be in addition to the deck replacement previously approved.
I look forward to seeing all of you on the Labor Day Cruise-In. Rumor has it that Team 3 has an outstanding weekend planned.
Ron
|